Return visit to a landmark location in Windsor
We’re back with an update for a return visit on a recent project completed before Christmas.
This phase of works
during strip out/ demolition, our client’s contractor encountered an unforeseen AIB panel, not listed/found on the initial R&D survey.
Work was promptly halted, and WestCross were contacted for a site visit to undertake bulk sample analysis and subsequently quote for these works.
The challenge of this project with no external parking available for our usual Decontamination Unit (DCU), we deployed our brand new modular unit, proving its worth when met with on site constraints. This challenge of restricted parking also led us to coordinate closely with our dedicated waste collection services, ensuring a smooth and compliant removal process for on site contractors and the general public.
A big well done to Billy and the team for their work on this project and to our construction partners for their continued trust in WestCross.